Drilling under way at Awarua as council tests backup water supply for Invercargill

Explore Invercargill News

By the Explore Invercargill news desk · Published Thursday 12 November 2026

Invercargill City Council is installing two more test bores at Awarua, where it is investigating an underground aquifer as a second water source for Invercargill and Bluff.

Where
Proposed alternate water supply site at Awarua
When
Drilling expected to finish by early 2027; pumping and monitoring to run for about three years
Cost
Phase 1 budget $23.9 million (Water Committee report)
Next step
Water permit application to Environment Southland planned for the end of November 2026

Every tap in Invercargill and Bluff is fed from the Ōreti River, and if that supply were cut, the city’s pipes and reservoirs hold enough for only a few days. The council’s Awarua Alternate Water Supply project is meant to give the community a fallback if that source is disrupted or there is an emergency.

The site at Awarua has had two test bores and two production wells since 2021, Earlier work there pointed to a deep aquifer that may be able to supply good-quality drinking water.

The council says the two new test bores are about measurement: tracking water levels and quality, and what happens to the land and water around the site when the aquifer is pumped.

Council General Manager Water Services Matt Keil said in the council’s announcement, “This work is a long-term investment in Invercargill and Bluff’s future water security, and our community’s essential infrastructure.”

A staged three-year pumping test

A project update to the council’s Water Committee meeting on Tuesday 3 November sets out the plan. The council intends to apply to Environment Southland for a five-year water permit, with the application due to be lodged at the end of November.

Timeline and what could change it

The report’s programme has the wells built and monitoring equipment in place by January 2027, consent granted around May 2027, pump testing starting in June 2027 and a first assessment of the aquifer’s capacity in July 2028. The council expects the current drilling to finish by early next year, depending on weather and ground conditions.

Get Invercargill’s news every Thursday

Explore Invercargill Weekly: local stories, weekend picks and what’s on. Free.

Free. One email a week. Unsubscribe any time.

Explore Invercargill Weekly

Local news, weekend picks and what’s on. Free every Thursday.

Free. One email a week. Unsubscribe any time.